| Mkataba | Mnunuzi | Aliyepewa tuzo | Thamani | Tarehe |
|---|---|---|---|---|
|
Construction of 32m span Mabatini bridge and its approaches road
|
Government of Tanzania (World Bank-financed, project P165660) | NYANZA ROAD WORKS LIMITED | 2,223,543 USD | 1 Nov 2024 |
|
Construction of Bridge (64m Span) and 2 Cells 5x4 Relief Box culverts at Mbwemkuru II
|
Government of Tanzania (World Bank-financed, project P165660) | JIANGXI GEO-ENGINEERING GROUP CORPORATION LIMITED | 5,381,565 USD | 1 Nov 2024 |
|
Construction of Miguruwe Bridge (40m) at Miguruwe and Relief box Relief culverts 1 Cell 1.5 x 1.5, 2 Cells 3x2...
|
Government of Tanzania (World Bank-financed, project P164920) | JIANGXI GEO-ENGINEERING GROUP CORPORATION LTD | 4,372,387 USD | 1 Nov 2024 |
|
Construction of Bridge (25m Span) and 2 Cells 5x4 Relief Box culverts at Kigombo
|
Government of Tanzania (World Bank-financed, project P165660) | MAKAPO CONTRACTORS & GENERAL SUPPLIES COMPANY LIMITED | 2,525,796 USD | 1 Nov 2024 |
|
Construction of Box culvets 1 Cell 5x2.5 at four Locations Ch. 27+100, 27+200, 27+300 and 27+800 2 Cells 5x4 a...
|
Government of Tanzania (World Bank-financed, project P165660) | M.E. AND COMPANY LIMITED | 2,398,833 USD | 1 Nov 2024 |
|
Construction of 2 Cell (5Mx4M) Box culvert at Kimanzichana along Kongowe - Malendego Road
|
Government of Tanzania (World Bank-financed, project P165660) | NYAKEMORE ENGINEERING AND SERVICE COMPANY LIMITED | 794,097 USD | 1 Nov 2024 |
|
Construction of Mikereng’ende Bridge (40m) and box culvert at Mtandango/Stakshari (2 Cells 4x2) and Masaninga...
|
Government of Tanzania (World Bank-financed, project P164920) | MAKAPO CONTRACTORS AND GENERAL SUPPLIES LTD | 3,851,923 USD | 1 Nov 2024 |
|
Construction of Kipwata Bridge (40m) and relief box culvert at Sakura and Songas (5m x 2.5m; 2 cell)
|
Government of Tanzania (World Bank-financed, project P164920) | HUNAN CONSTRUCTION ENGINEERING GROUP CO. LTD | 3,834,560 USD | 1 Nov 2024 |
|
Construction of Somanga Mtama Bridge (60m) and approach roads 1.7km
|
Government of Tanzania (World Bank-financed, project P164920) | HUNAN CONSTRUCTION ENGINEERING GROUP CO. LTD. | 4,488,126 USD | 1 Nov 2024 |
|
Construction of Box culvert – 2 cells of (5x4m), Bungu – Nyamisati Road (Msimbagenge Bridge)
|
Government of Tanzania (World Bank-financed, project P165660) | THE GLOBALINK GENERAL CONTRACTOR LTD | 1,140,230 USD | 1 Nov 2024 |
|
Construction of Box Culverts 4 cells sections (5mx4m) at Gama (GAMA-KISAUKE-SAADANI)
|
Government of Tanzania (World Bank-financed, project P165660) | MOTOSACH INTERNATIONAL (T) LIMITED | 703,100 USD | 1 Nov 2024 |
|
Construction of 2 (5x4m) Box culverts along Chalinze - Manga at Kimange including its approach road (250m)
|
Government of Tanzania (World Bank-financed, project P165660) | ANDIC LIMITED | 625,465 USD | 1 Nov 2024 |
|
Construction of Bridge (20m Span) and Relief Box culverts 2 Cells 2x2, 2 Cells 5x2.5, 2 Cells 5x4 at Nangano
|
Government of Tanzania (World Bank-financed, project P165660) | M.E. AND COMPANY LIMITED | 2,031,759 USD | 1 Nov 2024 |
|
Construction of Buiko Box Culvert with 2 cells of 5x2.5 and approach roads (50m) along Mkomazi JCT - Mkomazi W...
|
Government of Tanzania (World Bank-financed, project P165660) | GLODA CONSTRUCTION COMPANY LIMITED | 1,206,251 USD | 1 Nov 2024 |
|
Construction of Silwa Box culvert (5x2.5) two cells, including/milling, raise embankment, stabilisation, and l...
|
Government of Tanzania (World Bank-financed, project P165660) | TECHNICSCONSTRUCTION GROUP LIMITED | 1,064,725 USD | 1 Nov 2024 |
|
Construction of 45m span Kamishango Bridge and its approaches Road
|
Government of Tanzania (World Bank-financed, project P165660) | D.R.K GENERAL MERCHANTS LIMITED | 5,031,980 USD | 1 Nov 2024 |
|
CONSTRUCTION OF KABALISI BRIDGE 40M SPAN AND 5KM APPROACH ROADS ALONG KAFWAFWA-IBUNGU REGIONAL ROAD IN SONGWE...
|
Government of Tanzania (World Bank-financed, project P165660) | JASSIE & CO LIMITED | 2,941,532 USD | 1 Nov 2024 |
|
Construction of 15m span Mkuyuni bridge and its approaches road
|
Government of Tanzania (World Bank-financed, project P165660) | JASSIE & CO LIMITED | 1,924,207 USD | 1 Nov 2024 |
|
Construction of Chilonwa (Nzali) bridge and its approaches roads to gravel standard 1.5km along Chamwino Ikulu...
|
Government of Tanzania (World Bank-financed, project P165660) | M/S CHINA HEMAN INTERNATIONAL COOPERATION GROUP CO.LIMITED | 5,903,352 USD | 1 Nov 2024 |
|
Construction of 20m span Mkiri Bridge and its approach road of 20m length
|
Government of Tanzania (World Bank-financed, project P165660) | BR AND ASSOCIATES CONTRACTORS LIMITED | 1,184,884 USD | 1 Nov 2024 |
|
Construction of 45m span Mitomoni Bridge and its Approach Road (8.8km)
|
Government of Tanzania (World Bank-financed, project P165660) | OVANS CONSTRUCTION LIMITED | 3,442,164 USD | 1 Nov 2024 |
|
Lot 1: Construction of Bwage Bridge (25m span) along Mziha - Turiani - Magole and its approach roads; Lot 2: C...
|
Government of Tanzania (World Bank-financed, project P165660) | HALEM CONSTRUCTION COMPANY LIMITED | 3,973,365 USD | 1 Nov 2024 |
|
Construction of Nguyami Bridge (100m Span) Iyongwe -Chakwale - Ngiloli and Its Approach Roads
|
Government of Tanzania (World Bank-financed, project P165660) | KOBERG CONSTRUCTION COMPANY | 4,031,174 USD | 1 Nov 2024 |
|
Construction of Chakwale Bridge (80m Span) along Iyongwe - Chakwale - Ngiloli and its approach roads
|
Government of Tanzania (World Bank-financed, project P165660) | ASABHI COMPANY LIMITED | 3,102,810 USD | 1 Nov 2024 |
|
Construction of 16m span Bitimanyanga Bridge
|
Government of Tanzania (World Bank-financed, project P165660) | SUMMER COMMUNICATION LIMITED | 1,825,843 USD | 1 Nov 2024 |